Draining and filling the refrigerant
|
Draining and filling the refrigerant
|
Warning
|
Read through the following safety regulations before you start working on the A/C system.
|
•
|
Wear protective glasses and impermeable gloves, since there is a risk of burn and frost injuries.
|
•
|
If the skin comes into contact with the refrigerant, the exposed areas should be bathed in cold water and treated like a burn.
|
•
|
Should the coolant get into the eyes, they must be rinsed thoroughly with water for at least 10 minutes.
|
•
|
Refrigerant must not intentionally be released into the atmosphere. If, however, the refrigerant is unintentionally released in the premises, open and ventilate well before continuing work.
|
•
|
Gases that are formed when heating a refrigerant are a health hazard and can have a serious effect on the lungs.
|
•
|
Work should commence as soon as possible after emptying the A/C system as residual oil may emit refrigerant vapour that could collect and leak out if the work is delayed.
|
•
|
Smoking and open flames must not occur when handling refrigerants.
|
•
|
Refrigerant containers must not be exposed to heating, because the pressure will then increase resulting in the risk of explosion.
|
|
|
|
|
For information on the actual equipment, please refer to the manual of the equipment in question.
1.
|
Remove the protective covers from the high and low-pressure pipes.
|
2.
|
Attach the blue hose to the low-pressure pipe. Connect the red hose to the high-pressure pipe.
|
3.
|
The quick couplings are designed as so-called Schrader valves. Connection is therefore done in two steps:
|
|
•
|
Fit the quick coupling to the service connection.
|
|
•
|
Turn the handle clockwise, so that the valve opens and the refrigerant can pass through the connection.
|
4.
|
Begin draining the system. Follow the instructions for the machine in question. Note the amount of compressor oil drained.
|
5.
|
Close the cocks and disconnect the machine.
|
6.
|
Fit the protective covers to the high and low-pressure pipes.
|
1.
|
Remove the protective covers from the high and low-pressure pipes.
|
2.
|
Attach the blue hose to the low-pressure pipe. Connect the red hose to the high-pressure pipe.
|
3.
|
The quick couplings are designed as so-called Schrader valves. Connection is therefore done in two steps:
|
|
•
|
Fit the quick coupling to the service connection.
|
|
•
|
Turn the handle clockwise, so that the valve opens and the refrigerant can pass through the connection.
|
5.
|
For fully automatic filling
: Fill with compressor oil and tracing agent as described in the machine's instructions.
|
6.
|
Begin filling the systems. Follow the instructions for the machine.
|
7.
|
Close the cocks and disconnect the machine.
|
8.
|
Fit the service valves on the high-pressure and low-pressure pipes.
|